The specification for Planned Disbursement in the IATI standard states that they should include an updated time which is:
"The date on which this line of information was last updated. Previous updates for the same period should also be reported."
Does this mean that:
- Publishers might have more than one planned disbursement in their file for the same period.
- The planned disbursement should always be an aggregate of all disbursement planned for that period
- That any applications using the data should select only one planned disbursement record for any period, preferring the one with the most recent updated date?
5 Comments